Green Line Track and Intersection Upgrades (2020) | Projects (2024)

Green Line Track and Intersection Upgrades (2020) | Projects (1)

As part of Building a Better T 2020, we accelerated track work and intersection upgrades across the Green Line. We replaced 10.8 miles (24% of the Green Line) of track and upgrade 14 intersections (26% of the Green Line) on the B, C, and E branches.

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Why We Did This Work

Much of the Green Line tracks were over 30 years old and had reached the end of their service life. By replacing this track, we were able to lift speed restrictions across the line, saving riders a total of 4 minutes on their trips.

At intersections, we replaced uneven pavement with a new, smooth layer and installed accessible ramps where needed for improved rider experience, safety, and accessibility.

Work Locations and Schedule

Green Line B: Boston College to Babco*ck Street

Over four weekends in August and September (except Labor Day weekend), crews replaced 4,000 feet of track between Greycliff Road and Warren Street and upgraded an intersection and pedestrian crossing.

Each weekend, work started after service ended on Friday and was completed Monday morning before service resumed. There were be minor detours for pedestrians, bicyclists, and drivers during this work. There were also lane closures, and some parking spaces were temporarily unavailable. These restrictions were required for storing materials and accessing the tracks and likely occurred on the median side of the street.

From August 17 – 21, crews conducted overnight prep work for the weekend track and intersection upgrades. Work occurred between 9 PM – 5 AM, Monday through Friday, on Commonwealth Ave at Washington St.

Prep work involved welding segments of rail together and preparing the area for the upcoming weekend construction. While it did not affect Green Line B service, some of this work may have been noisy.

Find out what we're doing to minimize noise

LocationsDates
LocationsReplaced track between Washington Street and Warren StreetDates
  • August 29 – 30
  • September 12 – 13
  • September 19 – 20
LocationsUpgraded the Evergreen Cemetery intersection and pedestrian crossingDatesSeptember 19 – 20
LocationsColborne Road to Wallingford RoadDatesSeptember 26 – 27
  • Final summary: August 29 – September 28, 2020
  • Weekend 3 summary: September 19 – 20, 2020
  • Weekend 2 summary: September 12 – 13, 2020
  • Weekend 1 summary: August 29 – 30, 2020

Green Line C: Cleveland Circle – Kenmore

From July 6 – August 1, crews worked 24 hours a day, 7 days a week to rebuild intersections and rehabilitate more than two miles of track between Cleveland Circle and Kenmore. During the closure, one lane of general traffic on Beacon Street was designated as bus-only or bus- and bicycle-only wherever possible.

Download the C Branch fact sheet

LocationsDates
LocationsCoolidge Corner East and WestDatesMonday, July 6 – Sunday, July 12
LocationsWashington StDatesTuesday, July 7 – Friday, July 10
LocationsCleveland Circle to Englewood AveDatesThursday, July 9 and Monday, July 13 – Wednesday, July 15
LocationsDean Rd IntersectionDatesFriday, July 10 – Sunday, July 12
LocationsHarvard St IntersectionDatesThursday, July 16 – Monday, July 20
LocationsTappan StDatesMonday, July 20 – Wednesday, July 22
LocationsSt. Mary's to PortalDatesTuesday, July 21 – Sunday, July 26
LocationsGeneral maintenance work – all locationsDatesTuesday, July 28 – Saturday, August 1
  • Final summary: July 5 – August 1, 2020
  • Week 4 summary: July 25 – 31, 2020
  • Week 3 summary: July 18 – 24, 2020
  • Week 2 summary: July 11 – 17, 2020
  • Week 1 summary: July 5 – 10, 2020

Green Line E: Heath Street – Prudential

From August 2 – August 29, crews worked 24 hours a day, 7 days a week to rehabilitate track and intersections between Heath Street and Prudential. During this work, there were lane closures, and some parking spaces were temporarily unavailable. These restrictions were required for storing materials and accessing the tracks.

Download the E Branch fact sheet

Or choose your preferred language:

  • Español (Spanish)
  • Русский (Russian)
  • 汉语 (Chinese)

From July 20 – 31, Mondays – Fridays, 9 PM – 5 AM, overnight crews worked on Huntington Avenue near Parker Street/Forsyth Way. They welded segments of rail together, saw-cut pavement, and did other work to prepare for accelerated construction in August.

This overnight work did not affect Green Line E service, however, there were lane closures and limited parking.

LocationsDates
LocationsForsyth StDatesMonday, August 3 – Thursday, August 13
LocationsLongwood AveDatesThursday, August 6 – Monday, August 10
LocationsEvans WayDatesThursday, August 6 – Sunday, August 23
LocationsFire Dept Crossing & Ruggles St IntersectionDatesThursday, August 13 – Monday, August 17
LocationsForsyth Way (Parker St)DatesMonday, August 17 – Friday, August 21
LocationsHuntington Ave/South Huntington Ave CurveDatesThursday, August 20 – Tuesday, August 25
LocationsSouth Huntington AveDatesSunday, August 2 – Sunday, August 23
  • Final summary: August 2 – 29, 2020
  • Week 4 summary: August 22 – 28, 2020
  • Week 3 summary: August 15 – 21, 2020
  • Week 2 summary: August 8 – 14, 2020
  • Week 1 summary: August 2 – 7, 2020

What to Expect if You Live in the Neighborhood

The work along these 3 branches included replacing rail and repaving intersections. The noisiest work occured when crews cut the rails with a saw or torched and tamped the track to the proper elevation.

We used several strategies to minimize noise disruptions for neighbors, which included:

  • Assembling track panels off-site
  • Accessing work sites through the MBTA right of way
  • Using self-adjusting backup alarms, silencers, or mufflers on equipment
  • Limiting truck and equipment idling
  • Lining dumping bins, hoppers, and trucks with sound-deadening material
  • Using noise blankets and shielding where possible

We monitored noise levels and responded to all noise complaints. If you would like to report a noise issue, please call the 24/7 hotline at 508-676-3517.

Past Events

Green Line E Branch Track and Intersections Upgrades Virtual Public Meeting

July 23, 2020, 6:00 PM

Green Line E Branch Track and Intersections Upgrades Virtual Public Meeting

Virtual, Boston, MA

Green Line C Branch Track and Intersection Upgrades Virtual Public Meeting

June 29, 2020, 6:00 PM

Green Line C Branch Track and Intersection Upgrades Virtual Public Meeting

Virtual, Boston, MA

View all events

Contact Information

For all queries and comments related to Green Line Track and Intersection Upgrades (2020), please contactus atGLT@mbta.com.

If you would like to report a noise issue, call the 24/7 hotline at 508-676-3517.

For More Information

Get project news, updates, and information delivered to your inbox.

Recent Updates

See What We Completed During Two Weeks of Green Line C Shutdowns

Green Line Track and Intersection Upgrades (2020) | Projects (2)

July 24, 2020

See What We Completed During Two Weeks of Green Line C Shutdowns

View all project updates

Related Projects

Green Line Track and Intersection Upgrades (2020) | Projects (3)

This project is one of many we're working on to ensure twice as many passengers have access to a safer, more comfortable, and more reliable Green Line by 2030.

Learn more about the Green Line Program

Green Line Track and Intersection Upgrades (2020) | Projects (2024)

References

Top Articles
Latest Posts
Article information

Author: Otha Schamberger

Last Updated:

Views: 5688

Rating: 4.4 / 5 (55 voted)

Reviews: 94% of readers found this page helpful

Author information

Name: Otha Schamberger

Birthday: 1999-08-15

Address: Suite 490 606 Hammes Ferry, Carterhaven, IL 62290

Phone: +8557035444877

Job: Forward IT Agent

Hobby: Fishing, Flying, Jewelry making, Digital arts, Sand art, Parkour, tabletop games

Introduction: My name is Otha Schamberger, I am a vast, good, healthy, cheerful, energetic, gorgeous, magnificent person who loves writing and wants to share my knowledge and understanding with you.